4. Preventive Maintenance

PNNL's Preventive/Predictive Maintenance program describes the purpose, roles and responsibilities, and process for preventive maintenance at the Laboratory. The process for performing a PM is illustrated below:

The Facility Operations Building Core Team Facility Engineer determines when a PM is needed for facility equipment. Requests to include research equipment in the Preventive/Predictive Maintenance program are initiated through the Electronic Service Request system. PNNL has preventive maintenance procedures for various pieces of equipment including:

The preventive maintenance schedule is administered by the Integrated Business Operations organization within F&O to ensure that preventive maintenance is performed when needed. The Building Engineer assures that PM/PdM (preventive maintenance/predictive maintenance) documents are completed in an acceptable and timely manner. The facility project manager works with the Building Engineer to schedule and assign PM/PdM work, and the Work Control Specialist works with the Building Engineer to plan complex PM/PdM activities (see "Preventive/Predictive Maintenance Program").




| 1. Professional Expertise | 2. Safety and Health Rules | 3. Personal Protective Equipment |
| 4. Preventive Maintenance | 5. Emergency Preparedness | 6. Radiation Protection Program |
| 7. Medical Programs | 8. List of Occupational Safety and Health Programs |

Webmaster: Julie Fisher
Last Revision: June 20, 2001
Back to: VPP Application Site