Current Issues and Actions
D. G. Black
Progress has been made toward achieving full regulatory compliance at the Hanford Site. Ongoing
compliance self-assessments, implementation of the Tri-Party Agreement, and public meetings continue to
identify environmental compliance issues. These issues are discussed openly with the regulatory agencies and
with the public to ensure that all environmental compliance issues are addressed.
Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement)
Eighty-six milestones scheduled for 1994 were completed. Included in these completed milestones were the
activities below. The following were submitted to the regulators (Ecology and/or EPA):
- One closure plan for Hanford treatment, storage, and disposal facilities
- One remedial investigation report and plan
- Five limited field investigations
- Seven focused feasibility study reports
- Five interim remedial measures proposed plans
- 200 Area validated chemical and radiological data
- The 100-B Area burial ground test plan was submitted and field work was begun.
In 1994, the following activities were begun:
- Pilot-scale pump and treat operations for 100-HR-3 operable unit
- Analyses of core samples from single-shell tanks
- Operation of the 300 Area Treated Effluent Disposal Facility.
At the end of 1994, a total of 378 enforceable Tri-Party Agreement milestones (including 1989 through 1994)
had been completed on or ahead of schedule. Two milestones were missed and two were completed later than
scheduled.
Hanford Site cleanup began in 1989 with the signing of the Tri-Party Agreement. The Agreement laid out a
blueprint for the cleanup of the Hanford Site over a 30-year period. Over the past 5 years, the Agreement has
been changed as additional information has been acquired about the cleanup problems. The last major
changes occurred in January 1994, and focused primarily on the waste tanks at Hanford. As part of those
changes, the agencies agreed to take a comprehensive look at the environmental restoration program and the
future of unused facilities at Hanford.
A package of new negotiated changes to the Tri-Party Agreement was developed in January 1995. The new
requirements will establish 65 new enforceable milestones and 32 new unenforceable target dates.
A summary of the significant changes follows.
Environmental Restoration Proposed Changes
One of the strongest messages voiced by the public over the past several years has been to focus on cleanup
efforts along the Columbia River. To do this, the agencies need to redirect resources and funding to waste
sites near the Columbia River. The agencies are proposing to accelerate investigations and cleanup in the 100
and 300 Areas and defer investigation of many waste sites in the 200 Area. The 200 Area waste sites are
located on the central plateau, which is farther from the Columbia River than the 100 and 300 Areas. The
agencies will continue to address contaminated ground water throughout the Hanford Site.
In addition, the proposed changes seek to streamline regulatory processes at Hanford. Various waste sites in a
given geographic area would be cleaned up by coordinating regulatory requirements instead of using multiple
processes, which is the current method.
Specific Changes Proposed:
- Milestone M-13-00 requires the preparation and submittal of six remedial investigations/feasibility studies
each year. The sequence and types of submittals under this milestone will be modified to better
coordinate regulatory requirements and support the application of resources to the 100 and 300 National
Priorities List Areas.
- The 100-N Area will be used as a pilot project to ensure coordinated cleanup efforts. This cleanup will
reduce current and potential near-term impacts to human health and the environment from 100-N Area
facilities.
- The remedial investigation/feasibility study effort will be refocused to speed progress in achieving
stakeholders values, which includes protecting the Columbia River, implementing aggressive remedial
actions, and making land available for other uses.
- The completion of remediation of all operable units by September 2018 will be redefined to exclude the six
tank farm operable units. Remediation of these six units will be completed in the year 2024. The
remediation definition will be expanded to include the decontamination and decommissioning (final
disposition) of all facilities and structures excluding the 100 Area reactor buildings.
- The requirement for Part B RCRA permit applications and closure plans for certain RCRA treatment, storage,
or disposal units will be rewritten to optimize the efficiency of Site characterization and cleanup
activities.
Facility Transition Proposed Changes
When a facility will no longer be used for its original purpose, it will be brought into a safe and secure
condition that will minimize maintenance and surveillance expenses. This is facility transition. Transition is
the first phase of a three-step process called facility decommissioning. Phase I, transition, will include the
deactivation and stabilization of plant equipment and systems. Phase II, surveillance and maintenance, will
be the bridge period. Phase III, disposition, will be final closure and disposal of a facility. Any time before
disposition, a facility may be transferred to another useful purpose.
Until recently, the Tri-Party Agreement primarily addressed the cleanup of contaminated waste sites. In
January 1994, DOE agreed to include in the Tri-Party Agreement the disposition of key production and other
large Hanford facilities. The Tri-Party signatories began negotiations in July 1994 to set schedules and
milestones for cleanup at the PUREX and Uranium-TriOxide plants and the FFTF. The negotiations also
addressed the clean out of the Plutonium Finishing Plant and the 324 Building radiochemical engineering
cells and vault tanks.
A tentative agreement between DOE, EPA, and Ecology to proceed with facility transition and cleanup
actions under the Tri-Party Agreement was reached in January 1995 for all facilities except those in the 324
Building, which are still being negotiated.
Specific Changes Proposed:
- Establish a safe and environmentally secure configuration for the PUREX and Uranium-TriOxide plants to
achieve necessary preclosure actions and transition the facilities to the surveillance and maintenance
phase.
- Establish a safe and environmentally secure configuration for the Fast Flux Test Facility to achieve necessary
preclosure actions and transition the facilities to the surveillance and maintenance phase.
- Stabilize the previous process areas within the Plutonium Finishing Plant, including the Plutonium
Reclamation Facility and Remote Mechanical "C" Line. This will establish a safe and environmentally
secure configuration in these areas of the facility.
- Revise the necessary permitting, closure, or preclosure actions related to transition efforts for the PUREX
Plant, FFTF, and Plutonium Finishing Plant.
Other Proposed Modifications to the Tri-Party Agreement
Language will be added in Section 10 of the Tri-Party Agreement Action Plan that commits DOE to submit
key documents to the involved Native American tribes at the same time as they are submitted to Ecology and
EPA. New language is proposed in Sections 3, 5, 6, 7, and 9 of the Action Plan to support integration of
closure, past practice, and facility decommissioning activities. A number of terms will be added and other
definitions modified under Appendix A, Definition of Terms.
A new section, 14, will be added to the Action Plan to detail the facility decommissioning process. It will
include planning and action paths for all three decommissioning phases and will address regulatory
integration.
Hanford Summit II
More than 700 people attended Hanford Summit II, which was held in Pasco, Washington in June 1994. The
day-long event was a follow-up to the first Hanford Summit held in September 1993. The Secretary of
Energy's response to the Summit II initiatives was issued after extensive consultation and dialogue with
Summit participants.
Secretary of Energy Hazel O'Leary endorsed 26 Hanford Summit II initiatives to facilitate cleanup of the
Hanford Site. The initiatives cover such areas as regulatory reform, openness, training, public involvement,
and economic and technology development. The initiatives are also intended to create a sustainable economic
future for the Mid-Columbia region. The centerpiece of the Secretary's endorsement is a "demonstration
zone" to be established by the DOE, the EPA, and Ecology to integrate the various recommendations.
Secretary O'Leary said that the demonstration zone "will help display new ideas, new ways of doing business,
and new possibilities" for the nation's largest nuclear waste cleanup effort. Noting that the demonstration
zone complements Hanford's designation as a "laboratory" for reinventing government, the Secretary
encouraged the Richland Operations Office to begin implementation as soon as possible. Ideas proven to
make cleanup better, faster, safer, and more cost-effective would be applied across the Hanford Site,
throughout the DOE complex, and in some cases, to the commercial marketplace.
Other initiatives supported by the Secretary of Energy include:
- Streamlining regulations without compromising public safety, public involvement, or legal intent
- Maximizing public access to Hanford information
- Expediting declassification and release of documents from past DOE operations
- Continuing support of employee rights initiatives
- Working to increase stakeholder participation in the Hanford decision-making process
- Demonstrating and using new technologies
- Designing and constructing the Hazardous Materials Management and Emergency Response Center, subject
to Congressional line item funding
- Developing partnerships and other innovative practices. For example, in addition to a recent $987,000 grant
for an Entrepreneurship/Small Business Partnership, DOE will establish an Environmental Business
Enterprise Center and an Entrepreneurs Advisory Board, as well as specific relationships for technology
transfer. DOE endorsed school-to-work partnerships and other education initiatives, subject to funding
by the states or private sector.
Hanford Advisory Board
The Hanford Advisory Board was created in January 1994 to advise DOE on major Hanford cleanup policy
questions. The Board is one of 15 such advisory groups created by DOE at weapons production cleanup sites
across the complex. The Board comprises 33 members that represent a broad cross section of interests:
environmental, economic development, tribes and other governments, and the public. Each board member
has at least one alternate. Merilyn Reeves, of Amity, Oregon, is the chairperson.
The Board has six committees: 1) Dollars and Sense, which deals with DOE budget issues, 2) Public
Involvement, 3) Health, Safety, and Waste Management, 4) Environmental Restoration, 5) Cultural and
Socioeconomic Impacts, and 6) the Board's internal budget committee. Committees study issues and develop
policy recommendations for Board action.
Early on, the Board adopted and affirmed values developed by two predecessor groups: The Hanford Future
Site Use Working Group and the Tank Waste Task Force. The groups advised DOE and Hanford Site cleanup
regulators to 1) protect the Columbia River and 2) get on with cleanup. Board members have submitted
advice to DOE on a range of issues including budget priorities, environmental restoration, ground-water
monitoring and remediation, releases to the Columbia River via the N Springs, worker health and safety, local
economic transition issues, and public involvement.
Environmental and Molecular Science Laboratory
In 1994, ground was broken for the construction of the Environmental and Molecular Science Laboratory
(EMSL). When finished, the
(
) EMSL will accommodate up to 270 permanent staff,
visiting scientists, postdoctoral researchers, and students who will work to develop the science and technology
needed to clean up environmental problems at government and industrial sites across the country. Research
conducted at this national user facility is also expected to lead to advancements in energy, new materials,
health and medicine, and agriculture.
100-K Area Fuel Storage Basins
In February 1994, the Spent Nuclear Fuel Project was established. The project mission is to provide safe,
economic, and environmentally sound management of Hanford spent nuclear fuel in a manner that stages it to
final disposition.
The Hanford Site spent nuclear fuel inventory constitutes about 80% of the inventory currently stored in the
DOE complex. The majority of Hanford's inventory consists of about 2,100 metric tons (2,300 tons) of
irradiated N Reactor fuel stored in the 105 K-East and 105 K-West Fuel Storage Basins.
In 1994, working closely with stakeholders and local Native American tribes, decisions were made that
support a strategy for near-term and interim fuel storage of the K Basin inventory. This strategy supports
removal of the fuel and sludge from the K Basins before December 2002, as stipulated in the Tri-Party
Agreement. The Spent Nuclear Fuel Project is now in the process of implementing the strategy for
acceleration of fuel and sludge removal from the K Basins.
A project was started in 1994 to install isolation barriers in the basins. These barriers will isolate the spent
fuel from a vulnerable construction joint in the discharge chute of the basins to prevent the shielding water
from draining from the basins in the event of a major earthquake and releasing contaminated water to the
ground and radioactive contamination to the air. The project is expected to be complete in April 1995.
Plutonium Uranium Extraction and Uranium-TriOxide Plants
The function of the PUREX Plant was to treat irradiated reactor fuel elements to recover uranium and
plutonium-bearing solutions. In December 1992, DOE Headquarters directed the Richland Operations Office
to proceed with deactivation of the PUREX Plant. In September 1993, PUREX Plant management submitted
a project management plan to the Richland Operations Office for transition of the PUREX Plant to a
minimum surveillance mode, awaiting final decontamination and decommissioning. The transition is
expected to take approximately 5 years.
The Uranium-TriOxide Plant completed its final campaign in June 1993. During this campaign, 757,000 L
(200,000 gal) of liquid uranyl nitrate hexahydrate that had been in storage at the PUREX and
Uranium-TriOxide Plants were converted to approximately 199 metric tons (219 tons) of uranium-oxide
powder. The powder is being stored at the plant pending transfer to a vendor. In July 1993, 378,000 L
(100,000 gal) of recovered nitric acid were shipped back to the PUREX Plant. Flushing of residual process
solutions from the Uranium-TriOxide Plant piping and tanks was completed as part of the transition to
deactivation. This transition is expected to be complete by June 1995.
Plutonium Finishing Plant
The function of the Plutonium Finishing Plant (PFP) was to extract plutonium from plutonium-bearing
chemical solutions and convert it into metal and oxide. The PFP was first used in 1951, and the production
processes operated until May 1989. Although processing has ended, plutonium-bearing materials remain in
the plant.
In July 1993, DOE started discussions with citizens groups about plans to operate the PFP processes. DOE
intended to run processes within the PFP, the Plutonium Reclamation Facility, and portions of the Remote
Mechanical "C" Line to stabilize some plutonium-bearing materials. The Plutonium Reclamation Facility
would have purified plutonium solutions that would have been converted to plutonium dioxide in the Remote
Mechanical "C" Line. That operation would have involved release of 28-37 kg (60-80 lb) per day of carbon
tetrachloride to the air. DOE initiated efforts to prepare an environmental assessment to evaluate the action.
A series of public meetings regarding the proposed environmental assessment resulted in significant public
comment, demands for an EIS, and consideration of alternate methods of plutonium stabilization. Based on
these comments, DOE began preparing an EIS and approved a proposal to initiate several interim actions to
reduce safety risks in the facility while waiting for the EIS. These interim actions were selected because they
do not result in the production of a purified plutonium product, do not release carbon tetrachloride to the air
or discharge liquids to the ground, and create a much smaller amount of waste to be sent to Hanford's
double-shell tanks. Several of the interim actions have already been completed including downloading
solutions from the Plutonium Reclamation Facility for disposal, decontaminating portions of the PFP, and
removing plutonium-contaminated ducts and piping from the 232-Z incinerator building. Two interim actions
are ongoing:
- Sludge Stabilization--Much of the plutonium-bearing sludge stored in PFP gloveboxes can be heated and
converted to an impure stable solid and stored safely in PFP's vaults. An environmental assessment was
prepared to review potential impacts from this operation. The process uses two new small laboratory
furnaces to heat the sludge to about 1,0005C (1,8005F) over several hours. This process converts the
plutonium compounds to plutonium oxide and drives off the moisture, resulting in a stable oxide
powder. Other chemicals not driven off by the heating process remain as stable solids. Processing was
initiated in November 1994.
- Solutions in Storage Containers known as "10-Ls"--Some storage containers contain plutonium-bearing
chloride and fluoride solutions that pose special corrosion concerns. These solutions will be put in new,
safe storage containers. Some or all of the solutions will be used in the development laboratory to test
future processing options to support the EIS. Downloading these solutions is expected to start in early
1995.
Waste Vitrification
Approximately
(
) of radioactive and hazardous wastes accumulated from over 40
years of plutonium production operations are stored in 149 underground single-shell tanks and 28
underground double-shell tanks. Current plans are to pretreat the waste and then solidify it into a glass
matrix. Pretreatment will separate the waste into a low-radioactivity fraction, and a high-radioactivity and
transuranic fraction. The bulk of the radionuclides will then be in the high-radioactivity and transuranic
fraction. In separate facilities, both fractions will be vitrified, a process that will destroy or extract organic
constituents, neutralize or deactivate dangerous waste characteristics, and immobilize toxic metals. The
vitrified low-radioactivity fraction will be disposed of in a near-surface facility on the Hanford Site in a
retrievable form. The vitrified high-radioactivity fraction will be stored onsite until a geologic repository is
available offsite for permanent disposal. Tri-Party Agreement milestones specify December 2028 for
completion of pretreatment and vitrification of the tank wastes.
Waste Receiving and Processing Facility
During 1994, construction was started on the first major solid waste processing facility associated with
cleanup of the Hanford Site. Scheduled to begin operations in March 1997, the Waste Receiving and
Processing Facility Module 1 will be staffed to analyze, and prepare for disposal, drums and boxes of waste
resulting from plutonium operations at Hanford. The Tri-Party Agreement mandates construction and
operation of this module. Wastes destined for this module include Hanford's current inventory of more than
37,000 drums of stored waste, as well as materials generated by future site cleanup activities. Consisting
primarily of clothing, gloves, face masks, small tools, and dirt suspected of being contaminated with
plutonium, wastes in the
(55 gal) drums may also contain other radioactive materials and hazardous
components. Some of the materials processed will qualify as low-level waste suitable for disposal directly at
the Hanford Site. The remaining wastes will be certified and packaged for eventual shipment to the Waste
Isolation Pilot Plant in New Mexico. Materials requiring further processing to meet disposal criteria will be
retained at Hanford pending treatment.
The
(
) facility will begin operations in 1997 near the Central Waste Complex in the
200-West Area. The 200-West Area is located on the central plateau that the public and Tri-Party agencies
have designated for waste processing and long-term waste storage. The facility is designed to process 6,800
drums of waste annually for 30 years.
Waste Tank Safety Issues
The Waste Tank Safety Program (WTSP) was established in 1990 to address the hazards associated with
storage of radioactive mixed waste in the 177 large underground storage tanks at the Hanford Site. The
WTSP serves as the focal point for identification and resolution of selected high-priority waste tank safety
issues, with resolution being completed in priority order. Tanks with the highest risk will be evaluated and
mitigated first. The tasks to resolve the safety issue are planned and implemented in the following logic
sequences: 1) evaluate and define the associated safety issue, 2) identify and close any associated unreviewed
safety question (DOE 1991), 3) mitigate any hazardous condition to ensure safe storage of the waste, 4) store
and monitor waste conditions, and 5) resolve the respective safety issue. Each of these steps has supporting
functions of some combination of monitoring, mathematical analyses, laboratory studies, and in-tank
sampling or testing. The path followed is ultimately a function of whether the waste requires treatment and
where the treatment will take place.
The WTSP is currently focusing on resolution of ferrocyanide, flammable gas, organic, high-heat, noxious
vapor, and criticality safety issues as described below. The tanks of concern are placed on a Watch List by
safety issue. At the end of 1994, there were 54 tanks on the Watch List: 18 ferrocyanide tanks, 25 flammable
gas tanks, 20 organic tanks, and one high-heat tank. Some of the tanks are included under more than one
category. These tanks were identified in accordance with Public Law 101-510, Section 3137 (1990), Safety
Measures for Waste Tanks at Hanford Nuclear Reservation (the Wyden Amendment).
Watch List Tanks
In 1990, all Hanford Site high-level waste tanks were evaluated and organized into four categories of watch
list tanks to ensure increased attention and monitoring. Tanks were classified as ferrocyanide, flammable gas,
high-heat, and organic watch list tanks. Two other safety concerns that involve some or all of the tanks
include criticality and noxious vapor safety issues.
Ferrocyanide. The ferrocyanide safety issue involves the potential for uncontrolled exothermic reactions of
ferrocyanide and nitrate/nitrite mixtures (Postma et al. 1994a). Laboratory studies show that temperatures
must exceed 2505C for a reaction to propagate. The hottest ferrocyanide tank temperature is 5305C and
decreasing. In October 1990, an unreviewed safety question was declared because safety was not adequately
defined by then existing analyses. However, the unreviewed safety question was closed by DOE in March
1994, as a result of significant knowledge gained from simulant studies, conservative theoretical analyses, and
analyses of actual waste samples that allowed bounding safety criteria to be defined and applied to each tank
(Postma et al. 1994a). Of the original 24 ferrocyanide tanks, 18 are now on the watch list. Four were
removed in 1993 and two were removed in 1994. The remaining tanks will be taken off the watch list as core
samples are obtained and analytical analyses confirm that the ferrocyanide has decreased in fuel content from
hydrolysis and radiolysis ("aging") to acceptable low levels (Lilga et al. 1994, Meacham et al. 1995).
Flammable Gas. The flammable gas tanks safety issue involves the potential release of flammable gases
from wastes in selected tanks. In prior years, work controls were instituted to prevent introduction of spark
sources in these tanks, and evaluations were completed to ensure that installed equipment was intrinsically
safe. The worst-case tank, 241-SY-101, was successfully mitigated in 1994 with the insertion of a mixing
pump. The pump is operated up to three times a week to mix the waste and release gases that accumulate in
the waste. Hydrogen monitors are being installed on all 25 flammable gas tanks. These monitors, called
standard hydrogen monitoring systems, consist of a cabinet equipped with piping and instrumentation that
support an on-line hydrogen detector and a "grab sampler." Documentation to close the unreviewed safety
question in the 241-SY tank farm is being prepared and will be submitted to DOE early in 1995 for closure
action.
High-Heat Tank. This safety issue concerns tank 241-C-106, a single-shell tank that requires water additions
and forced ventilation for evaporative cooling. Without the water additions, which would be discontinued in
the event of a tank leak, the tank could exceed structural temperature limits, resulting in potential concrete
degradation and possible tank collapse. This tank is on an accelerated program for early retrieval and transfer
of waste to a double-shell tank. Double-shell tanks are designed to handle heat-bearing materials better than
single-shell tanks. A process test and considerable thermal analyses were completed in 1994 on tank
241-C-106 to evaluate alternative cooling approaches (Eyler 1994, Thurgood et al. 1995). The studies
concluded that the tank could be adequately cooled using refrigerated air chillers.
Organic Tanks. The organic tanks safety issue involves the potential for uncontrolled exothermic reactions
of organic chemicals and nitrates/nitrites and for vapors from semivolatile organics entrained in the waste to
exceed the flammability limits. Recent laboratory tests showed that fuel concentrations and temperatures
required to support propagating exothermic reactions are comparable to those for ferrocyanide. In addition,
moisture levels above 20% will prevent reactions from propagating regardless of fuel concentrations.
Work controls were implemented in 1990 to prevent the introduction of ignition sources to these tanks. In
May 1994, vapor sampling and safety analyses were completed that provided the technical basis for closing
the unreviewed safety question on the flammability of the floating organic layer in tank 241-C-103 (Postma et
al. 1994b). Ten tanks that contained organic complexants were added to the organic tanks watch list
following a review of sampling data and waste transfer records (Hanlon 1994).
Other work indicates that aging processes have also destroyed or significantly lowered the energy content of
the organic tanks (Ashby et al. 1994). In addition, work by Barney (1994) shows that the more energetic
complexants and the primary degradation products of tributyl phosphate (TBP) are water soluble in saturated
nitrate-nitrite salt solutions. Thus, a high percentage of organic chemicals were removed from the single-shell
tanks when their pumpable liquid supernatant was pumped out as part of the interim stabilization process for
the single-shell tanks.
Criticality. The unreviewed safety question on the potential for criticality in the high-level waste tanks was
closed in 1994 by completing additional analyses, strengthening tank criticality prevention controls, and
improving administrative procedures and training (Braun and Szendre 1994). The analyses showed that
criticality is highly unlikely during storage. All of the single- and double-shell tanks at the Hanford Site
contain sufficient neutron absorbers to ensure safe storage; however, additional sampling and controls will be
required for retrieval and pretreatment-related activities.
Noxious Vapor. Some of the Hanford Site tanks contain chemicals that release toxic vapors to the
environment. These vapors pose a potential health risk to Hanford Site employees who work in the tank
farms. The safety issue stems from an insufficient understanding of the causes of reported exposures of
personnel to unacceptable levels of noxious vapors and the concern that, until the vapors in the tanks are well
characterized, the risks to worker health and safety cannot be determined or controlled (Osborne 1994,
Huckaby and Babad 1994). In prior years, worker protection controls were instituted to prevent worker
exposures, and a program was implemented for routine workspace air monitoring and personnel dosimetry.
In-tank vapor sampling equipment was developed and tested in 1994. Two methods are now used to collect
vapor samples from the waste tanks (Huckaby 1994). The primary method involves drawing air, gases, and
vapors out of the waste tanks. This method was designed to collect representative samples from warm, moist
tanks, even if a fog exists in the tank headspace. A second method employs in situ sampling. Rather than
transferring the air, gases, and vapors to be sampled to a remote location, the sampling devices themselves
(specifically, sorbent traps) are lowered into the tank headspace. Through 1994, 18 high-level waste tanks
were vapor sampled using these two methods.
Waste Tank Status
The status of the 177 waste tanks as of December 1994 is reported in WHC-EP-0182-81, Waste Tank
Summary for Month Ending December 31, 1994 (Hanlon 1995). This report is published monthly; the
December report provided the following:
- Number of waste tanks
- 149 single-shell tanks
- 28 double-shell tanks
- Number of tanks listed as "assumed leaker" tanks
- 67 single-shell tanks
- 0 double-shell tanks
- Chronology of single-shell tank leaks
- 1956: First tank reported as suspected of leaking (Tank 241-U-104)
- 1973: Largest estimated leak reported (Tank 241-T-106; 435,000 L [115,000 gal])
- 1988: Tanks 241-AX-102, -C-201, -C-202, -C-204, and -SX-104 reported as confirmed leakers
- 1992: Latest tank (241-T-101) added to assumed leaker list, bringing total to 67 single-shell tanks
- 1994: Tank 241-T-111 declared an assumed re-leaker
- Number of ferrocyanide tanks on watch list
- 18 single-shell tanks(a) (two tanks [241-BX-102 and -BX-106] were removed from the watch list in
December 1994)
- Number of flammable gas tanks on watch list
- 19 single-shell tanks(b)
- 6 double-shell tanks
- Number of organic tanks on watch list
So far, 106 single-shell tanks have been stabilized, with the program to be completed in 2000. At the end of
1994, 98 single-shell tanks had intrusion prevention devices completed, and 51 single-shell tanks were partial
interim isolated.
The total estimated volume of radioactive waste leakage from single-shell tanks is 2,270,000 to 3,410,000 L
(600,000 to 900,000 gal).
During 1994, two single-shell tanks identified as assumed re-leaker tanks were pumped as discussed below.
Tank 241-BX-111. This tank was declared an assumed re-leaker in April 1993. Pumping of the tank
commenced in October 1993, and was completed in April 1994. Pumping was restarted in May to remove
additional pumpable liquid after review of in-tank photos. A total of 436,000 L (115,000 gal) were pumped
from the tank in 1994 with completion of interim stabilization expected in 1995.
Tank 241-T-111. The surface level showed a steady decrease after the automatic waste surface level
measurement device was repaired in August 1993. The surface level measurement after the repair was 4.11 m
(13.5 ft) and continued to decrease to 4.09 m (13.4 ft) through January 1994. An off-normal occurrence
report was issued in February 1994, and the tank was declared an assumed re-leaker. Pumping began in May
1994, completing a Tri-Party Agreement milestone for the start of emergency pumping. A total of 29,900 L
(7,900 gal) was pumped from the tank in 1994 with completion of interim stabilization expected in 1995.
During 1994, pumping occurred in eight single-shell tanks. In addition to the two tanks listed above, tanks
241-BX-110, 241-BY-102, 241-BY-109, 241-C-102, 241-C-107, and 241-C-110 were also pumped. In 1994,
the total liquid volume removed from the eight tanks was 490,000 L (129,000 gal).
Pollution Prevention Program
The Hanford Site Pollution Prevention Program (formerly Waste Minimization) is an organized,
comprehensive, and continual effort to systematically reduce the quantity and toxicity of hazardous,
radioactive, mixed, and sanitary wastes; conserve resources and energy; reduce hazardous substance use; and
prevent or minimize pollutant releases to all environmental media from all operations and Site cleanup
activities.
It is designed to satisfy DOE requirements, recent presidential executive orders, and other state and federal
regulations and requirements. In accordance with sound environmental management, preventing pollution
through source reduction is the first priority in the Hanford Site's Pollution Prevention Program, and the
second priority is environmentally safe recycling. Waste treatment to reduce the quantity, toxicity, or mobility
(or a combination of these) will be considered only when prevention or recycling are not possible or practical.
Environmentally safe disposal is the last option.
By incorporating this hierarchy into Hanford environmental management activities, the following successes in
minimizing waste were accomplished:
- Hanford Site pollution prevention efforts in 1994 helped to prevent the generation of
(
)
of radioactive mixed waste, 133 metric tons (147 tons) of RCRA waste, and 17,700 metric tons (19,500
tons) of sanitary waste with a cost savings of approximately $4 million.
- Two separate modifications in liquid scintillation measurement techniques accounted for a
(
)
reduction in radioactive mixed waste. The use of a microscintillation counter allowed a 99% reduction
in materials used for some sample measurements, and the substitution of a nonregulated scintillation
cocktail reduced the waste classification from radioactive mixed to low-level radioactive waste.
- The Hazardous Materials Reduction Initiative avoided the purchase of 900 kg (2000 lb) of hazardous
products, recycled more than 10 metric tons (11 tons) of surplus materials, and eliminated the use of
more than 2.5 metric tons (1.7 tons) of products containing Class I ozone depleting substances.
- During 1994, the Hanford Site recycled offsite 610 metric tons (670 tons) of office paper; 1,800 metric tons
(2000 tons) of scrap metal; 59 metric tons (65 tons) of lead; 9,500 toner cartridges for computer printers,
and 8,300 L (2200 gal) and 50 metric tons (55 tons) of surplus chemical products.
Besides these sitewide programs, numerous generator-specific initiatives were put into place. These
initiatives are specific to a particular area or process and, in most cases, were thought of and implemented by
the onsite people who handle the waste daily. To celebrate these pollution prevention activities, the "Pollution
Prevention Accomplishments Book" (Betsch 1994) was published in October covering activities in 1994.
This book outlines 33 significant initiatives that were implemented and are now in use at locations throughout
the Hanford Site. A few of these initiatives are:
- Replaced alkaline and NiCd batteries with rechargeable alkaline batteries
- Avoided mixed waste by diverting rainwater away from areas where it would become contaminated
- Eliminated custodial services' use of all hazardous cleaning products, thereby avoiding the resulting regulated
waste
- Recycled radiological signs into plastic pipe.
These activities, plus 29 others, resulted in significant reductions in hazardous waste, radioactive waste, and
solid sanitary waste, and promoted resource conservation and technology transfer. Most of the ideas were
simple improvements in processes enacted by changing the methods of remediation or disposal. The focus
was on generating less waste in the first place and reusing or recycling the waste that was generated.
Although not all the waste savings from these generator-specific ideas were quantifiable, those that were
resulted in the following reductions:
- 8,730 million L (2,310 million gal) of bulk liquid
(
) of solid waste
kilojoules (
kilowatt-hours) of energy.
These reductions are estimated for all of 1994. In addition to these and the nonquantifiable waste reductions,
numerous other benefits were realized, including significant cost savings of more than $43 million, reduced
worker exposure, improved public relations, and an overall improvement in quality of operations.
242-A Evaporator Status
The 242-A Evaporator was restarted as scheduled in April 1994 and completed two waste reduction
campaigns. Each campaign processed the low-level mixed waste contents of six double-shell tanks. The
evaporator process resulted in an average waste reduction of 85% in tank waste volume. The process
condensate from the evaporator operation is stored in the Liquid Effluent Retention Facility and is awaiting
final disposal through the 200 Area Effluent Treatment Facility. Future campaigns have been scheduled for
1995 and 1996.
Liquid Effluent Activities
Liquid Effluent Retention Facility
The start-up activities for the Liquid Effluent Retention Facility were completed on time to support the 242-A
Evaporator campaigns in 1994. As a result of these campaigns, 25,000,000 L (6,600,000 gal) of evaporator
process condensate are stored in the Liquid Effluent Retention Basins awaiting final processing through the
200 Area Effluent Treatment Facility. The Liquid Effluent Retention Facilities consist of three separate
(
) storage basins (surface impoundments). Two are used for normal operation, and the
third is used as a contingency in the event a leak should develop in an operational basin.
Ecology requested that the 242-A Evaporator, the Liquid Effluent Retention Facility, and the 200 Area
Effluent Treatment Facility RCRA Part B permit applications be integrated into one permit application. The
Richland Operations Office concurred with Ecology's request.
200 Area Effluent Treatment Facility, Project C-018H
The 242-A Evaporator/PUREX Plant Process Condensate Treatment Facility (200 Area Effluent Treatment
Facility) is being constructed to provide effluent treatment and disposal capability required to restart the
242-A Evaporator. The facility will provide for effluent collection, a treatment system to reduce the
concentration of radioactive and hazardous waste constituents in the effluent streams to acceptable levels,
tanks to allow verification of treated effluent characteristics before discharge, and a state-approved land
disposal structure for effluents.
Secondary waste generated by the treatment facility will be concentrated and packaged to meet state
requirements for storage and/or disposal of solid waste.
Acceptance testing of the facility began in late 1994 and is expected to be completed in March 1995. The
facility is expected to begin operations in October 1995. All regulatory permit applications required for the
facility and disposal site have been submitted to the regulators as required in the Tri-Party Agreement and
Ecology Liquid Effluent Consent Order (No. DE 91NM-177). Because process condensate was not available
for waste characterization, the Federal Delisting Petition, the State Waste-water Discharge Permit, and the
RCRA Dangerous Waste Permit applications were based on a surrogate solution. This surrogate was
developed and tested under pilot-scale conditions to determine a list of constituents that the facility can
successfully treat.
200 Area Treated Effluent Disposal Facility, Project W-049H
The 200 Area Treated Effluent Disposal Facility will be a permitted system for the collection, sampling, and
disposal of 13 effluent streams in the 200-East and 200-West Areas. Based on data derived in preparing the
Washington Administrative Code 173-240-130 Engineering Report required by the State Waste-Water
Discharge Permit program, it has been determined that the best available technology and all known and
reasonable methods of prevention, control, and treatment will be implemented at each waste-water generating
facility. Effluents will meet the requirements of best available technology before being discharged to the
collection and disposal system. The construction of the collection system began in April 1993 and is now
complete: final testing of the system is ongoing. The disposal facility design is complete.
300 Area Treated Effluent Disposal Facility
The 300 Area Treated Effluent Disposal Facility was completed and in operation in December 1994, ahead of
schedule and under budget. It satisfied Tri-Party Agreement milestone M-17-09 for ceasing the discharge of
untreated 300 Area process sewer effluent to the soil column at the 300 Area Process Trenches. A National
Pollutant Discharge Elimination System permit has been issued by EPA Region 10 that allows the facility to
discharge treated effluents to the Columbia River. The permit contains a reopener clause such that, after one
year of operation, permit conditions may be renegotiated.
The 300 Area Treated Effluent Disposal Facility has a 1200 L/min (320 gal/min) treatment capacity. The
facility, operated 24 hrs, is largely computer automated, with the capability for full manual operation.
After its collection, the process waste water is treated for metals, suspended solids, residual mercury and
heavy metals, organics, nitrite, sulfides, cyanide, and pH before discharge via a subsurface river diffuser in
the Columbia River near Johnson Island. Sludge from the process is packaged in drums, and disposed of in a
landfill.
340 Facility
The 340 Facility collects radionuclides and mixed wastes from the 300 Area for transportation to tank farms
via rail car. Radioactive mixed liquid wastes that are collected originate at Pacific Northwest National Laboratories and are critical
to tank waste safety, tank characterization, and Site remediation. The 340 Facility tanks are currently
operated as less than 90-day accumulation tanks under the requirements of the Dangerous Waste Regulations,
WAC 173-303.
Phase II Effluent Streams
As part of the October 1991 negotiations to supplement the Tri-Party Agreement and to create the Consent
Order (No. DE 91NM-177), the Richland Operations Office committed by October 1997, to implement the
best available technology and all known and reasonable methods of prevention, control, and treatment
(BAT/AKART) for the remaining nine Phase II streams, and to permit the streams under the WAC 173-216
State Waste-Water Discharge Permit Program. A WAC 173-240-130 Engineering Report was submitted to
Ecology in September 1992.
One stream, the 241-AY/AZ Steam Condensate, is discharged to the Tank Farms and is not planned for
discharge to the ground. Another stream, the 183-D Filter Backwash, was eliminated in June 1994. A State
Waste-Water Discharge Permit application for 400 Area Secondary Cooling Water was submitted to Ecology
in December 1992. The permit is expected to be issued in 1995.
The scope of the BAT/AKART for the 200 Area Phase II Streams is to eliminate, minimize, or treat effluents
currently being discharged to the 216-B-3 Expansion Ponds. The facilities involved include the 241-A Tank,
the 242-A Evaporator, the 244-AR Vault, B Plant, and the 284-E Powerhouse. The conceptual design report
was completed in June 1993. Advanced conceptual design was completed in January 1995, with definitive
design starting in February 1995. A State Waste-Water Discharge Permit application for these streams was
submitted to Ecology in December 1993.
Miscellaneous Streams
In accordance with Ecology Consent Order (No. DE 91NM-177), the DOE Richland Operations Office
committed to submit State Waste-Water Discharge Permit applications for eleven miscellaneous streams. A
decision was made to instead obtain a National Pollutant Discharge Elimination System permit for two of
these streams for discharge to the Columbia River (300 Area Powerhouse Ash Waste Water, and Filter
Backwash). Other changes included the decision to connect the 300 Area Sanitary Sewer to the City of
Richland Publically Owned Treatment Works, and the decision to connect the 234-5Z Ventilation Steam
Condensate/Dry Air Compressor Cooling Water to the 200 Area Treated Effluent Disposal Facility. The
209-E Building Steam Condensate stream was eliminated. State Waste-Water Discharge Permit applications
were submitted to Ecology in June 1994 for the remaining six miscellaneous streams.
The DOE Richland Operations Office also agreed to inventory the remaining miscellaneous streams and to
develop a plan and schedule for the disposition of those streams. An inventory of all effluent streams was
developed that identified more than 500 small discharges. These discharges were evaluated against criteria
developed to determine if they had any potential to cause harm to the environment or ground water. This
inventory and these criteria were used to develop the final overall plan and schedule for regulatory
compliance, which was submitted to Ecology in December 1994.
Submarine Reactor Compartments
Eight defueled submarine reactor compartment disposal packages were received and placed in Trench 94 in
the 200-East Area during 1994. This brings the total number received to 43.
The reactor compartment disposal packages are being regulated by Ecology as dangerous waste because of
the presence of lead used as shielding and by EPA because of the presence of small amounts of PCBs bound
within the matrix of nonmetallic materials such as thermal insulation, electrical cables, and some synthetic
rubber items.
Revegetation
The U.S. Army Corps of Engineers is currently working with the Natural Resources Trustee Council, PNL,
and the Nature Conservancy on the preparation of a habitat/revegetation plan for the Hanford Site.
Revegetation of selected sites is expected to occur in 1995.
Self-Assessments
During 1994, 249 environmental compliance self-assessments were completed by WHC. Approximately a
third of these self-assessments identified compliance deficiencies such as deficiencies with hazardous waste
management and effluent monitoring. Corrective actions for each of these deficiencies were also identified
for completion.
PNL completed 36 environmental compliance self-assessments in 1994. Unsatisfactory conditions were
identified in 14 of the assessments. The conditions all dealt with hazardous waste management issues. The
majority of the conditions have been rectified, and corrective action is in progress for the remainder.
Return to Table of Contents
(a) Two ferrocyanide tanks are also listed as organic tanks.
(b) Eight flammable gas tanks are also listed as organic tanks.